HOME    ·  SITEMAP    ·   CONTACT US

Welcome to the City of Nolanville

A Great Place to Live

 

 

Capital Improvements 

Capital Improvement Certificate of Obligation (CO), July 2020 $1,500,000 

Capital Improvement Projects (CIP) address Nolanville’s long-term needs in the form of street repairs, drainage improvements, parks, other public utilities and facilities. These projects are typically scheduled over several years to address the City’s ability to pay for the improvements. Capital Improvement Projects are relatively expensive and non-recurring, periodically these improvements are financed with Bonds or Certificates of Obligation.

The 2020 Obligation will primarily fund road construction. A 20% match is required for TxDOT Livability Project "Nolanville Park Connectivity" (concepts of the project are shown above).  The project extends from 10th Street along Avenue H and the entire length of Mesquite Street. The total project is estimated at $1.5 million, the City's Match is $300,000 (funded through CO plus engineering (funded through Street Maintenance Fund.)

The remaining portion of the CO is planned for reconstructing the remainder of Avenue H to Jackrabbit, a portion of the side streets in the plaza and engineering for Old Nolanville Bridge and East/West Tributaries

Public Works Street Preservation

Viking Construction applied micro-surfacing to various streets throughout the City November 2019 to improve ride ability and preservation.  Streets treated included Ashly, Gehler, Jordan Loop, Moss and Cindy. 

Additional streets will receive preservation coat in the Summer of 2020.  The target area is the Ridges. 

Pleasant Hill Road was widened at the entrance and repaved to improve safety from the access road March 2019, work was completed by TTG.

Point repairs were completed  January 2019 and June 2020 throughout the City. Alpha Paving is completing the work. 

Tax Note 2017, $500,000

In March 2017, a Public Works Bond (7 Year) was issued for $500,000, intended for various projects involving Road & Drainage Improvements. Below is a summary of these efforts:

Red Leaf Drainage:  This problem was identified and engineered in 2016.  It was ready to bid for construction and completed the Summer of 2017.

Park Road, Elm and West Dogwood Drainage & Road Reconstruction:  Solving the drainage issues on these roads was the main focus of the Bond.  Residents were notified and asked to park on the streets during critical times of the road reconstruction.  There were several fences obstructing drainage and maintenance, the City is coordinating with owners to remove them temporarily and replace with flow through design.  Park road is also carved out.  Substantial completion is just around the corner.

Blue Bonnet Spillway:  Construction was completed April 2019.

Walkability Improvements.

- Old Nolanville Road- Safe Routes to  School is a TxDOT Grant that funds 80% of improvements that will provide sidewalks, widening of the road for shared use and bus stop improvements.   Road failures occurred that were not part of the original scope of work, Public Works Street Repair funds were used to offset the cost of the additional work.  The project was completed in July 2018.

- Main Street Connectivity- Adds sidewalks, multi modal access and improved safety along Main Street.  Sidewalks extends to the bus stops. This grant is from KTMPO/TxDOT covers 80% of construction, the 20% match is funded by the Economic Development Corporation.  The project was completed in April 2019..

Governor's Community Achievement Award
Nolanville won the Governor's Community Achievement Award for Keep Nolanville Beautiful efforts in 2017.  KNB the award is $110,000 for Landscaping on Main Street. If you would like to be part of these efforts contact nedc@ci.nolanville.tx.us or attend a meeting on the 4th Thursday of the month at 6pm, Nolanville Municipal Building.

Don't Forget Important Dates!
  • Day
  • Week
  • Month
  • Agenda
  • Categories
    • Select All
    • City Council Meetings
    • Planning & Zoning Commission Meetings
    • WCID #3 Water Board Meetings
    • Special Events
    • Holidays
    • Election
    • Zoning Board of Adjustment Meetings
    • Economic Development Board Meetings
  • Print
  • iCal
  • RSS
July 2020
Previous Month July 2020Next Month
Sun Mon Tue Wed Thu Fri Sat
28
29
30
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
1

Interstate 14 Improvements

The I-14 project, adding roadway capacity via an inside travel lane in both the eastbound and westbound directions as well as a concrete traffic barrier between opposing travel lanes, from FM 3423 (Indian Trail) in Harker Heights to FM 2410 in Belton, began in September 2019 and is scheduled for completion in the summer of 2021, weather permitting.   

TxDOT advises the traveling public to expect delays, temporary congestion and periodic temporary single lane closures within the work zone, for the duration of the project.  


The project, designed to increase safety along US 190, will apply safety-end-treatments to culvert-ends at cross drainage locations under frontage roads and adjoining private driveways, as well as upgrade guard-rail from Paddy Hamilton Road, east of Nolanville, to I-35 at Belton.

Please observe all warning signs and exercise caution when passing near construction personnel and equipment in the project area.

Park Improvements
- Texas Parks & Wildlife granted a $150,000 grant match for a splash park and playground improvements in 2016. The EDC contributed an overmatch for $23,000.  

- The City received an award for continuing phases of the improvement in March of 2018.  The grant will be used to provide sports lighting/fields, skate park, and many other long overdue elements.   The basketball court will be completed in February 2019. Multi-use field was substantially complete  March 2020 to include a ADA walking trail. 

- The Multi-Use Center was funded by the Texas Department of Agriculture as a Community Development Block Grant.  The grant provided $350,000 and the EDC provided the 5% match of $17,500, while the City contributed $20,000 toward construction.  The Boys & Girls Club began operations in the building on August 24, 2018

Subscribe to Our Newsletter

Receive periodic Nolanville Updates to your email.  Sign Up Below

Email:

Copyright © 2016 City of Nolanville, Texas.

powered by ezTaskTitanium TM